Section 1 STRUCTURE AND MAST, ACCESSORIES |
1.1 |
Mast |
JJ225/43-K |
|
Specifications: |
|
|
n Available height: |
43.2m |
|
n Static hook load capacity: |
2250KN |
|
n Width of top (front x side)M(in) |
2/2m(79×79) |
|
n Width of bottom: |
8m(26) |
|
n Height of racking platform m(ft): |
24.5, 25.5, 26.5m(87,83.7,80.4) |
|
n Anti-wind capacity: |
|
|
No setback, no hook load km/h (NMPH) |
172 (93) |
|
Full setback, no hook load km/h (nmph) |
130 (70) |
|
Mast erecting or lowering down km/h (nmph) |
30 (16) |
|
Ø No hook load, full of stands: |
36m/s |
|
Ø No hook load, no stand: |
47.8m/s |
|
Ø Lifting and lowering: |
8.3m/s |
1.2 |
Crown block |
TC225 |
1.3 |
Casing stabbing board |
|
1.4 |
Substructure |
DZ225/7.5-K |
|
n Floor height: |
7.5m |
|
n Floor area: |
10.66m×9.84m |
|
n Available height below R/Table beam: |
6.26m |
|
n Max. Capacity of R/Table beam: |
2250KN |
|
n Setback capacity (4-1/2” drilling pipe, 28m stand): |
4000m |
|
n Setback load: |
1440kN |
1.5 |
BOP Trolley unit |
|
1.6 |
Mouse hole |
|
1.7 |
Rat hole |
|
1.8 |
Hydraulic power station |
|
1.9 |
Hydraulic cathead |
|
1.10 |
Derrick escape device fixed on Monkey board |
|
1.11 |
Derrick man anti-dropping device |
|
1.12 |
Mast and substructure adopts oil cylinder as buffer. It consists of oil cylinder, control cansole and pipeline, etc. |
|
1.13 |
Tools and accessories for rig installation |
|
1.14 |
Dead line anchor |
|
1.15 |
Air winch on racking board |
0.8 Mpa 5KN |
1.16 |
Air winch on rig floor |
|
1.17 |
Accessory parts |
|
1.18 |
CCTV system |
|
1.19 |
COMMUNICATION system |
|
1.20 |
Cat walk |
|
1.21 |
Dog house: |
|
1.22 |
Tool house: |
|
Features of 1000hp drilling rig
1. DW, RT and mud pump realize independent DC stepless speed regulation which provide guarantee for drilling technology optimization.
2. Mast, substructure and drill floor equipments can be installed at lower position, and then be lifted integrally upon DW power.
3. Auto-bit-feeding adopts all-digital auto control technique, driller operates the touch screen to fulfill drilling operation through optimized drilling parameters, which will reduce labor intensity significantly and improve work efficiency. Display, restoration, regulation and control, remote management of major drilling parameters can be realized.